Substation Scout

MISO request J3852

MISO queue ID J3852

Queue request J3852 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW solar project in Tuscola County, MI, according to Berkeley Lab’s queue data file. The filing names KIRK as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2030.

Queue IDJ3852
Project nameNot reported
Status (as published)Active
SubstationKIRK
Point of interconnectionKIRK
CountyTuscola
StateMI
VoltageNot reported
Capacity200 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2030-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tuscola, MI: 25 requests in the MISO queue, 15 active totaling 2,038.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC
ClusterDPP Cycle Pending East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-12-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first