Substation Scout

MISO request J3848

MISO queue ID J3848

Queue request J3848 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW battery project in Wabasha County, MN, according to Berkeley Lab’s queue data file. The filing names Wabaco as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2030.

Queue IDJ3848
Project nameNot reported
Status (as published)Active
SubstationWabaco
Point of interconnectionWabaco
CountyWabasha
StateMN
VoltageNot reported
Capacity250 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2030-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Wabasha, MN: 6 requests in the MISO queue, 3 active totaling 500 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDAIRYLAND POWER COOPERATIVE
ClusterDPP Cycle Pending West
Interconnection serviceNRIS
Project typeGeneration
Queue date2024-12-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.