MISO request J3552
MISO queue ID J3552
Queue request J3552 was listed in the MISO interconnection queue at the end of 2025 as a 112 MW solar project in Mcleod County, MN, according to Berkeley Lab’s queue data file. The filing names Hutchinson Municipal - GRE Big Swan as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 31, 2028.
| Queue ID | J3552 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Hutchinson Municipal - GRE Big Swan |
| Point of interconnection | Hutchinson Municipal - GRE Big Swan 115.0kV |
| County | Mcleod |
| State | MN |
| Voltage | 115 kV |
| Capacity | 112 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2028-10-31 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Mcleod, MN: 9 requests in the MISO queue, 3 active totaling 282.2 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | MISSOURI RIVER ENERGY SERVICES - TRANSMISSION |
|---|---|
| Cluster | DPP-2023 West |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | In Progress (unknown study) |
| Study phase (as the queue printed it) | Study Phase: DPP 1 |
| Queue date | 2024-04-16 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.