Substation Scout

MISO request J3552

MISO queue ID J3552

Queue request J3552 was listed in the MISO interconnection queue at the end of 2025 as a 112 MW solar project in Mcleod County, MN, according to Berkeley Lab’s queue data file. The filing names Hutchinson Municipal - GRE Big Swan as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 31, 2028.

Queue IDJ3552
Project nameNot reported
Status (as published)Active
SubstationHutchinson Municipal - GRE Big Swan
Point of interconnectionHutchinson Municipal - GRE Big Swan 115.0kV
CountyMcleod
StateMN
Voltage115 kV
Capacity112 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-10-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mcleod, MN: 9 requests in the MISO queue, 3 active totaling 282.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMISSOURI RIVER ENERGY SERVICES - TRANSMISSION
ClusterDPP-2023 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: DPP 1
Queue date2024-04-16

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.