Substation Scout

MISO request J3523

MISO queue ID J3523

Queue request J3523 was listed in the MISO interconnection queue at the end of 2025 as a 115 MW battery project in Barron County, WI, according to Berkeley Lab’s queue data file. The filing names BARRON - WASHCO as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 30, 2028.

Queue IDJ3523
Project nameNot reported
Status (as published)Active
SubstationBARRON - WASHCO
Point of interconnectionBARRON - WASHCO 161.0kV
CountyBarron
StateWI
Voltage161 kV
Capacity115 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2028-09-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

BARRON - WASHCO substation: 2 requests in the MISO queue, 1 active totaling 115 MW.

Queue IDProjectMWResourceStatus
J3433Not reported115SolarWithdrawn

Barron, WI: 5 requests in the MISO queue, 4 active totaling 495 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDAIRYLAND POWER COOPERATIVE
ClusterDPP-2023 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: DPP 1
Queue date2024-04-16

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.