Substation Scout

MISO request J348

MISO queue ID J348

Queue request J348 was listed in the MISO interconnection queue at the end of 2025 as a 81 MW hybrid project in Arkansas County, AR, according to Berkeley Lab’s queue data file. The filing names Entergy Stuttgart Rcuskey-Almyra115 kv line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 1, 2016.

Queue IDJ348
Project nameNot reported
Status (as published)Operational
SubstationEntergy Stuttgart Rcuskey-Almyra115 kv line
Point of interconnectionEntergy Stuttgart Rcuskey-Almyra115 kv line
CountyArkansas
StateAR
Voltage115 kV
Capacity81 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2016-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Arkansas, AR: 22 requests in the MISO queue, 7 active totaling 1,021 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2014-AUG South
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2014-05-19
Interconnection agreement date2015-09-14
Operational date2016-09-01
Components (hybrid)Solar 81 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first