MISO request J348
MISO queue ID J348
Queue request J348 was listed in the MISO interconnection queue at the end of 2025 as a 81 MW hybrid project in Arkansas County, AR, according to Berkeley Lab’s queue data file. The filing names Entergy Stuttgart Rcuskey-Almyra115 kv line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of September 1, 2016.
| Queue ID | J348 |
|---|---|
| Project name | Not reported |
| Status (as published) | Operational |
| Substation | Entergy Stuttgart Rcuskey-Almyra115 kv line |
| Point of interconnection | Entergy Stuttgart Rcuskey-Almyra115 kv line |
| County | Arkansas |
| State | AR |
| Voltage | 115 kV |
| Capacity | 81 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2016-09-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Arkansas, AR: 22 requests in the MISO queue, 7 active totaling 1,021 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Cluster | DPP-2014-AUG South |
|---|---|
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Network Upgrade |
| Queue date | 2014-05-19 |
| Interconnection agreement date | 2015-09-14 |
| Operational date | 2016-09-01 |
| Components (hybrid) | Solar 81 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.