Substation Scout

MISO request J3448

MISO queue ID J3448

Queue request J3448 was listed in the MISO interconnection queue at the end of 2025 as a 180 MW wind project in Grant County, WI, according to Berkeley Lab’s queue data file. The filing names NELSON DEWEY (ATC) - GRAN GRAE (ATC) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 31, 2028.

Queue IDJ3448
Project nameNot reported
Status (as published)Active
SubstationNELSON DEWEY (ATC) - GRAN GRAE (ATC)
Point of interconnectionNELSON DEWEY (ATC) - GRAN GRAE (ATC) 161.0kV
CountyGrant
StateWI
Voltage161 kV
Capacity180 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2028-08-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Grant, WI: 18 requests in the MISO queue, 8 active totaling 950 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDAIRYLAND POWER COOPERATIVE
ClusterDPP-2023 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: DPP 1
Queue date2024-04-18

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first