Queue request J343 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW wind project in Adams County, IA, according to Berkeley Lab’s queue data file. The filing names substation on Creston-Clarinda line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of August 1, 2016.

Queue IDJ343
Project nameNot reported
Status (as published)Operational
Substationsubstation on Creston-Clarinda line
Point of interconnection161 kv substation on Creston-Clarinda line
CountyAdams
StateIA
Voltage161 kV
Capacity150 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2016-08-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Adams, IA: 4 requests in the MISO queue, 1 active totaling 150 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2014-AUG West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2014-05-19
Interconnection agreement date2016-05-09
Operational date2016-08-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.