Substation Scout

MISO request J3286

MISO queue ID J3286

Queue request J3286 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW solar project in Sanilac County, MI, according to Berkeley Lab’s queue data file. The filing names KILGORE - MICAH as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 1, 2028.

Queue IDJ3286
Project nameNot reported
Status (as published)Active
SubstationKILGORE - MICAH
Point of interconnectionKILGORE - MICAH 120.0kV
CountySanilac
StateMI
Voltage120 kV
Capacity200 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Sanilac, MI: 23 requests in the MISO queue, 11 active totaling 2,361.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC
ClusterDPP-2023 East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)In Progress (unknown study)
Study phase (as the queue printed it)Study Phase: DPP 1
Queue date2024-04-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.