Queue request J3224 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW hybrid project in Marion County, IL, according to Berkeley Lab’s queue data file. The filing names 4KINMUNDY-4TANNER as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 1, 2026.
| Queue ID | J3224 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | 4KINMUNDY-4TANNER |
| Point of interconnection | 4KINMUNDY-4TANNER 138kv |
| County | Marion |
| State | IL |
| Voltage | 138 kV |
| Capacity | 150 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2026-08-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Marion, IL: 7 requests in the MISO queue, 4 active totaling 549 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | AMEREN ILLINOIS |
|---|---|
| Cluster | DPP-2022 Central |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | Cluster Study |
| Study phase (as the queue printed it) | Study Phase: DPP 2; Post GIA Status: Not Started |
| Queue date | 2022-09-15 |
| Components (hybrid) | Solar 150 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.