MISO request J3186

MISO queue ID J3186

Queue request J3186 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW hybrid project in Bolivar County, MS, according to Berkeley Lab’s queue data file. The filing names Rosedale - Delta as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of January 1, 2027.

Queue IDJ3186
Project nameNot reported
Status (as published)Active
SubstationRosedale - Delta
Point of interconnectionRosedale - Delta 115 kV
CountyBolivar
StateMS
Voltage115 kV
Capacity100 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2027-01-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Bolivar, MS: 8 requests in the MISO queue, 3 active totaling 360 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY MISSISSIPPI, LLC.
ClusterDPP-2022 South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-15
Components (hybrid)Solar 100 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.