MISO request J3158

MISO queue ID J3158

Queue request J3158 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW battery project in Cerro Gordo County, IA, according to Berkeley Lab’s queue data file. The filing names Colby Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2027.

Queue IDJ3158
Project nameNot reported
Status (as published)Active
SubstationColby Substation
Point of interconnectionColby 345 kV Substation
CountyCerro Gordo
StateIA
Voltage345 kV
Capacity100 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2027-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cerro Gordo, IA: 22 requests in the MISO queue, 8 active totaling 3,339.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-14

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.