Substation Scout

MISO request J3058

MISO queue ID J3058

Queue request J3058 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW hybrid project in Arkansas County, AR, according to Berkeley Lab’s queue data file. The filing names TARLETON as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 6, 2025.

Queue IDJ3058
Project nameNot reported
Status (as published)Active
SubstationTARLETON
Point of interconnectionTARLETON
CountyArkansas
StateAR
VoltageNot reported
Capacity200 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2025-12-06
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Arkansas, AR: 22 requests in the MISO queue, 7 active totaling 1,021 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
ClusterDPP-2022 South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2025-07-28
Components (hybrid)Solar 200 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first