Substation Scout

MISO request J3028

MISO queue ID J3028

Queue request J3028 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW hybrid project in Perry County, MS, according to Berkeley Lab’s queue data file. The filing names Waynesboro 161 - Hintonville 161 as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2027.

Queue IDJ3028
Project nameNot reported
Status (as published)Active
SubstationWaynesboro 161 - Hintonville 161
Point of interconnectionWaynesboro 161 - Hintonville 161 161.0kV
CountyPerry
StateMS
Voltage161 kV
Capacity100 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2027-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Perry, MS: 7 requests in the MISO queue, 3 active totaling 500 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityCOOPERATIVE ENERGY
ClusterDPP-2022 South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-14
Components (hybrid)Solar 100 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first