MISO queue ID J301

Queue request J301 was listed in the MISO interconnection queue at the end of 2025 as a 101 MW wind project in Tuscola County, MI, according to Berkeley Lab’s queue data file. The filing names ITCs Bauer-Rapson line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of July 1, 2017.

Queue IDJ301
Project nameNot reported
Status (as published)Operational
SubstationITCs Bauer-Rapson line
Point of interconnectionITCs Bauer-Rapson 345kV line
CountyTuscola
StateMI
Voltage345 kV
Capacity101 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2017-07-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Tuscola, MI: 25 requests in the MISO queue, 15 active totaling 2,038.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2015-FEB East (ITC)
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Int FaS
Queue date2013-11-18
Interconnection agreement date2016-07-06
Operational date2017-07-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.