MISO queue ID J2990

Queue request J2990 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Pottawattamie County, IA, according to Berkeley Lab’s queue data file. The filing names Overland - J1859 POI Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 15, 2025.

Queue IDJ2990
Project nameNot reported
Status (as published)Active
SubstationOverland - J1859 POI Line Tap
Point of interconnectionOverland - J1859 POI 345kV Line Tap
CountyPottawattamie
StateIA
Voltage345 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2025-06-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Pottawattamie, IA: 12 requests in the MISO queue, 1 active totaling 200 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY CO.
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-14

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first