Substation Scout

MISO request J292

MISO queue ID J292

Queue request J292 was listed in the MISO interconnection queue at the end of 2025 as a 3,576 MW hydro project in Churchill County, MB, according to Berkeley Lab’s queue data file. The filing names Limestone, Long Spruce and Kettle Generating Statiosn as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 1, 2016.

Queue IDJ292
Project nameNot reported
Status (as published)Operational
SubstationLimestone, Long Spruce and Kettle Generating Statiosn
Point of interconnectionLimestone, Long Spruce and Kettle Generating Statiosn
CountyChurchill
StateMB
VoltageNot reported
Capacity3,576 MW
Resource (as published)Hydro
Resource categoryHydro (normalized for filtering)
Proposed online date2016-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Churchill, MB: 1 request in the MISO queue, 1 active totaling 3,576 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2014-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)DPP - SIS
Queue date2013-08-13
Interconnection agreement date2015-09-01
Operational date2016-10-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first