Queue request J2886 was listed in the MISO interconnection queue at the end of 2025 as a 115 MW hybrid project in Sangamon County, IL, according to Berkeley Lab’s queue data file. The filing names 4Auburn N-4Jacksnvl as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 1, 2026.

Queue IDJ2886
Project nameNot reported
Status (as published)Active
Substation4Auburn N-4Jacksnvl
Point of interconnection4Auburn N-4Jacksnvl 138kV
CountySangamon
StateIL
Voltage138 kV
Capacity115 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2026-11-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Sangamon, IL: 20 requests in the MISO queue, 11 active totaling 2,627.7 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2022 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-15
Components (hybrid)Solar 115 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first