MISO request J2757

MISO queue ID J2757

Queue request J2757 was listed in the MISO interconnection queue at the end of 2025 as a 160.3 MW solar project in Cherokee County, IA, according to Berkeley Lab’s queue data file. The filing names LITTLE SIOUX - CLIPPER as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 1, 2026.

Queue IDJ2757
Project nameNot reported
Status (as published)Active
SubstationLITTLE SIOUX - CLIPPER
Point of interconnectionLITTLE SIOUX - CLIPPER 161.0kV
CountyCherokee
StateIA
Voltage161 kV
Capacity160.3 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-05-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Cherokee, IA: 4 requests in the MISO queue, 1 active totaling 160.3 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY CO.
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2025-10-17

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.