Substation Scout

MISO request J2641

MISO queue ID J2641

Queue request J2641 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Jackson County, AR, according to Berkeley Lab’s queue data file. The filing names NEWPORT as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 1, 2025.

Queue IDJ2641
Project nameNot reported
Status (as published)Active
SubstationNEWPORT
Point of interconnectionNEWPORT
CountyJackson
StateAR
VoltageNot reported
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2025-10-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Jackson, AR: 22 requests in the MISO queue, 10 active totaling 3,580 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
ClusterDPP-2022 South
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-15

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first