Substation Scout

MISO request J263

MISO queue ID J263

Queue request J263 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW wind project in Stutsman County, ND, according to Berkeley Lab’s queue data file. The filing names OTP Jamestown 345/ Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of October 27, 2014.

Queue IDJ263
Project nameNot reported
Status (as published)Operational
SubstationOTP Jamestown 345/ Substation
Point of interconnectionOTP Jamestown 345/115 kV Substation
CountyStutsman
StateND
Voltage115 kV
Capacity100 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2014-10-27
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Stutsman, ND: 12 requests in the MISO queue, 6 active totaling 746 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2013-FEB West
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2013-01-07
Interconnection agreement date2014-12-07
Operational date2014-10-27

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first