Substation Scout

MISO request J2553

MISO queue ID J2553

Queue request J2553 was listed in the MISO interconnection queue at the end of 2025 as a 210 MW solar project in Cerro Gordo County, IA, according to Berkeley Lab’s queue data file. The filing names Killdeer as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2026.

Queue IDJ2553
Project nameNot reported
Status (as published)Active
SubstationKilldeer
Point of interconnectionKilldeer
CountyCerro Gordo
StateIA
VoltageNot reported
Capacity210 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Killdeer substation: 4 requests in the MISO queue, 4 active totaling 2,533.2 MW.

Queue IDProjectMWResourceStatus
J4113Not reported1,315GasActive
E0049Not reported798.2GasActive
J2811Not reported210SolarActive

Cerro Gordo, IA: 22 requests in the MISO queue, 8 active totaling 3,339.2 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
ClusterDPP-2022 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2022-09-14

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first