Substation Scout

MISO request J232

MISO queue ID J232

Queue request J232 was listed in the MISO interconnection queue at the end of 2025 as a 35 MW coal project in Randolph County, IL, according to Berkeley Lab’s queue data file. The filing names Baldwin Station as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of May 25, 2018.

Queue IDJ232
Project nameNot reported
Status (as published)Operational
SubstationBaldwin Station
Point of interconnectionBaldwin Station
CountyRandolph
StateIL
VoltageNot reported
Capacity35 MW
Resource (as published)Coal
Resource categoryCoal (normalized for filtering)
Proposed online date2018-05-25
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Randolph, IL: 9 requests in the MISO queue, 4 active totaling 452.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

ClusterDPP-2012-AUG
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Network Upgrade
Queue date2011-11-09
Interconnection agreement date2013-11-01
Operational date2018-05-25

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first