Queue request J2261 was listed in the MISO interconnection queue at the end of 2025 as a 625 MW solar project in Jackson County, AR, according to Berkeley Lab’s queue data file. The filing names INDEPENDENCE-ISES - POWERLINE ROAD as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2028.

Queue IDJ2261
Project nameNot reported
Status (as published)Active
SubstationINDEPENDENCE-ISES - POWERLINE ROAD
Point of interconnectionINDEPENDENCE-ISES - POWERLINE ROAD 500.0kV
CountyJackson
StateAR
Voltage500 kV
Capacity625 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

INDEPENDENCE-ISES - POWERLINE ROAD substation: 5 requests in the MISO queue, 3 active totaling 1,800 MW.

Queue IDProjectMWResourceStatus
J2262Not reported625SolarActive
J2478Not reported550SolarActive
J3626Not reported500SolarWithdrawn
J3073Not reported200BatteryWithdrawn

Jackson, AR: 22 requests in the MISO queue, 10 active totaling 3,580 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY ARKANSAS
ClusterDPP-2021 South
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2021-10-11
Interconnection agreement date2025-12-11

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first