Substation Scout

MISO request J2189

MISO queue ID J2189

Queue request J2189 was listed in the MISO interconnection queue at the end of 2025 as a 15.6 MW wind project in Mcdonough County, IL, according to Berkeley Lab’s queue data file. The filing names Hornsby Switching Station as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 1, 2019.

Queue IDJ2189
Project nameNot reported
Status (as published)Active
SubstationHornsby Switching Station
Point of interconnectionHornsby Switching Station
CountyMcdonough
StateIL
VoltageNot reported
Capacity15.6 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2019-12-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mcdonough, IL: 9 requests in the MISO queue, 4 active totaling 565.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2021 Central
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Study Phase: DPP 2; Post GIA Status: Not Started
Queue date2021-08-17

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first