MISO request J2133
MISO queue ID J2133
Queue request J2133 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW hybrid project in White County, AR, according to Berkeley Lab’s queue data file. The filing names Garner Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 15, 2024.
| Queue ID | J2133 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Garner Substation |
| Point of interconnection | Garner 115 kV Substation |
| County | White |
| State | AR |
| Voltage | 115 kV |
| Capacity | 100 MW |
| Resource (as published) | Solar+Battery |
| Resource category | Hybrid (normalized for filtering) |
| Proposed online date | 2024-04-15 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
White, AR: 8 requests in the MISO queue, 4 active totaling 395 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY ARKANSAS |
|---|---|
| Cluster | DPP-2021 South |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Pending |
| Study phase (as the queue printed it) | Study Phase: GIA In Process; Post GIA Status: Not Started |
| Queue date | 2021-08-26 |
| Components (hybrid) | Solar 100 MW + Battery |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.