MISO request J1814

MISO queue ID J1814

Queue request J1814 was listed in the MISO interconnection queue at the end of 2025 as a 22.5 MW solar project in Dickinson County, MI, according to Berkeley Lab’s queue data file. The filing names Nordic as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 15, 2026.

Queue IDJ1814
Project nameNot reported
Status (as published)Active
SubstationNordic
Point of interconnectionNordic
CountyDickinson
StateMI
VoltageNot reported
Capacity22.5 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-09-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Nordic substation: 4 requests in the MISO queue, 3 active totaling 70.5 MW.

Queue IDProjectMWResourceStatus
J4085Not reported42SolarActive
J4169Not reported6SolarActive
J3642Not reported60SolarWithdrawn

Dickinson, MI: 10 requests in the MISO queue, 5 active totaling 163 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP-2020 East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2020-06-24
Interconnection agreement date2024-02-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.