Substation Scout

MISO request J1773

MISO queue ID J1773

Queue request J1773 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW wind project in Lafayette County, WI, according to Berkeley Lab’s queue data file. The filing names Hill Valley to Cardinal as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2027.

Queue IDJ1773
Project nameNot reported
Status (as published)Active
SubstationHill Valley to Cardinal
Point of interconnectionHill Valley to Cardinal 345kV
CountyLafayette
StateWI
Voltage345 kV
Capacity300 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2027-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Lafayette, WI: 11 requests in the MISO queue, 4 active totaling 594 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP-2020 East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2020-06-22
Interconnection agreement date2024-02-28

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first