Substation Scout

MISO request J1746

MISO queue ID J1746

Queue request J1746 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW solar project in Columbia County, WI, according to Berkeley Lab’s queue data file. The filing names Columbia as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 12, 2028.

Queue IDJ1746
Project nameNot reported
Status (as published)Active
SubstationColumbia
Point of interconnectionColumbia 138 kV
CountyColumbia
StateWI
Voltage138 kV
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2028-06-12
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Columbia substation: 6 requests in the MISO queue, 4 active totaling 795.2 MW.

Queue IDProjectMWResourceStatus
J4144Not reported525GasActive
J2761Not reported100SolarActive
R5066Replacing 20 MW of solar with storage; J174620.2HybridActive
J1884Not reported200BatteryWithdrawn
J2062Not reported100SolarWithdrawn

Columbia, WI: 33 requests in the MISO queue, 13 active totaling 2,565.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMERICAN TRANSMISSION COMPANY
ClusterDPP-2020 East (ATC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2020-06-24
Interconnection agreement date2024-10-07

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.