Substation Scout

MISO request J1721

MISO queue ID J1721

Queue request J1721 was listed in the MISO interconnection queue at the end of 2025 as a 175.1 MW solar project in Vigo County, IN, according to Berkeley Lab’s queue data file. The filing names TH Pfizer Jct. - Worthington (HED) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2026.

Queue IDJ1721
Project nameNot reported
Status (as published)Active
SubstationTH Pfizer Jct. - Worthington (HED)
Point of interconnectionTH Pfizer Jct. - Worthington (HED)
CountyVigo
StateIN
VoltageNot reported
Capacity175.1 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

TH Pfizer Jct. - Worthington (HED) substation: 4 requests in the MISO queue, 1 active totaling 175.1 MW.

Queue IDProjectMWResourceStatus
J3494Not reported175SolarWithdrawn
J3285Not reported150SolarWithdrawn
J2360Not reported90BatteryWithdrawn

Vigo, IN: 23 requests in the MISO queue, 12 active totaling 2,973.8 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityDUKE ENERGY INDIANA
ClusterDPP-2020 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2020-06-24

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.