MISO request J1701

MISO queue ID J1701

Queue request J1701 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW wind project in Mcdonough County, IL, according to Berkeley Lab’s queue data file. The filing names Macomb to Ipava line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 15, 2026.

Queue IDJ1701
Project nameNot reported
Status (as published)Active
SubstationMacomb to Ipava line
Point of interconnectionMacomb to Ipava 138kV line
CountyMcdonough
StateIL
Voltage138 kV
Capacity200 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2026-09-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Mcdonough, IL: 9 requests in the MISO queue, 4 active totaling 565.6 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2020 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2021-12-03
Interconnection agreement date2025-06-05

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.