MISO request J1671

MISO queue ID J1671

Queue request J1671 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW solar project in Walker County, TX, according to Berkeley Lab’s queue data file. The filing names Rocky Creek to Lewis Creek as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 4, 2025.

Queue IDJ1671
Project nameNot reported
Status (as published)Active
SubstationRocky Creek to Lewis Creek
Point of interconnectionRocky Creek to Lewis Creek 230kV
CountyWalker
StateTX
Voltage230 kV
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-12-04
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Walker, TX: 5 requests in the MISO queue, 1 active totaling 150 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY TEXAS, INC.
ClusterDPP-2020 South
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Under Construction
Queue date2020-06-23
Interconnection agreement date2024-12-13

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.