Queue request J1576 was listed in the MISO interconnection queue at the end of 2025 as a 200 MW solar project in Washington Parish, LA, according to Berkeley Lab’s queue data file. The filing names Angie to Adams Creek as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of November 1, 2026.
| Queue ID | J1576 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Angie to Adams Creek |
| Point of interconnection | Angie to Adams Creek 230 kV |
| County | Washington Parish |
| State | LA |
| Voltage | 230 kV |
| Capacity | 200 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2026-11-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Washington Parish, LA: 17 requests in the MISO queue, 5 active totaling 550 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | ENTERGY LOUISIANA |
|---|---|
| Cluster | DPP-2020 South |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Study Phase: GIA In Process; Post GIA Status: Not Started |
| Queue date | 2022-03-03 |
| Interconnection agreement date | 2023-01-18 |