Substation Scout

Washington Parish, LA interconnection queue

5 active projects totaling 550 MW in the MISO queue, plus 12 with terminal status (shown grayed).

5active projects
550active MW
17total filed
Queue IDProjectkVMWResourceStatus
J3055 Not reported 500 250 Solar Withdrawn
J1576 Not reported 230 200 Solar Active
J3054 Not reported 500 200 Solar Withdrawn
J3056 Not reported 500 200 Hybrid Withdrawn
J2743 Not reported n/r 175 Solar Withdrawn
J2643 Not reported 115 150 Solar Active
J1506 Not reported 230 100 Solar Withdrawn
J1564 Not reported 230 100 Solar Active
J1906 Not reported n/r 100 Battery Withdrawn
J3211 Not reported n/r 100 Hybrid Withdrawn
J1184 Not reported 115 50 Solar Active
J1361 Not reported 115 50 Solar Active
J1433 Not reported 115 50 Solar Withdrawn
J1505 Not reported 230 50 Battery Withdrawn
J1507 Not reported 230 50 Battery Withdrawn
J2642 Not reported 115 50 Battery Withdrawn
J559 Not reported 115 50 Solar Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →