Substation Scout

MISO request J1529

MISO queue ID J1529

Queue request J1529 was listed in the MISO interconnection queue at the end of 2025 as a 50 MW solar project in Carroll County, IA, according to Berkeley Lab’s queue data file. The filing names Tap Carroll - Auburn line at about midpoint as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 15, 2026.

Queue IDJ1529
Project nameNot reported
Status (as published)Active
SubstationTap Carroll - Auburn line at about midpoint
Point of interconnectionTap Carroll (635320) - Auburn (635328) 69 kV line at about midpoint
CountyCarroll
StateIA
Voltage69 kV
Capacity50 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2026-09-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Carroll, IA: 4 requests in the MISO queue, 2 active totaling 250 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY CO.
ClusterDPP-2020 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2021-04-16
Interconnection agreement date2024-08-05

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first