MISO request J1485

MISO queue ID J1485

Queue request J1485 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW wind project in Deuel County, SD, according to Berkeley Lab’s queue data file. The filing names Astoria Substation (J493/J510) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 30, 2022.

Queue IDJ1485
Project nameNot reported
Status (as published)Active
SubstationAstoria Substation (J493/J510)
Point of interconnectionAstoria 345 kV Substation (J493/J510)
CountyDeuel
StateSD
Voltage345 kV
Capacity250 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2022-10-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Deuel, SD: 23 requests in the MISO queue, 6 active totaling 2,320.7 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityOTTER TAIL POWER COMPANY
ClusterDPP-2019 West
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Pending
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2019-04-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.