MISO request J1432

MISO queue ID J1432

Queue request J1432 was listed in the MISO interconnection queue at the end of 2025 as a 250 MW wind project in Clinton County, IA, according to Berkeley Lab’s queue data file. The filing names Salem - Rock Creek Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of September 1, 2025.

Queue IDJ1432
Project nameNot reported
Status (as published)Active
SubstationSalem - Rock Creek Line
Point of interconnectionSalem - Rock Creek 345kV Line
CountyClinton
StateIA
Voltage345 kV
Capacity250 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2025-09-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Clinton, IA: 12 requests in the MISO queue, 7 active totaling 1,260 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
ClusterDPP-2019 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2019-04-29
Interconnection agreement date2022-10-31

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.