Substation Scout

MISO request J1401

MISO queue ID J1401

Queue request J1401 was listed in the MISO interconnection queue at the end of 2025 as a 150 MW solar project in Branch County, MI, according to Berkeley Lab’s queue data file. The filing names Batavia - Wagner Line as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of April 1, 2024.

Queue IDJ1401
Project nameNot reported
Status (as published)Operational
SubstationBatavia - Wagner Line
Point of interconnectionBatavia - Wagner 138kV Line
CountyBranch
StateMI
Voltage138 kV
Capacity150 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2024-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Branch, MI: 17 requests in the MISO queue, 13 active totaling 3,125 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMETC
ClusterDPP-2019 East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: In Service
Queue date2019-04-29
Interconnection agreement date2022-08-17
Operational date2024-04-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first