MISO request J1399
MISO queue ID J1399
Queue request J1399 was listed in the MISO interconnection queue at the end of 2025 as a 90 MW solar project in Ingham County, MI, according to Berkeley Lab’s queue data file. The filing names Delhi - Churchill - Tompkins Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of March 1, 2025.
| Queue ID | J1399 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Delhi - Churchill - Tompkins Line |
| Point of interconnection | Delhi - Churchill - Tompkins 138kV Line |
| County | Ingham |
| State | MI |
| Voltage | 138 kV |
| Capacity | 90 MW |
| Resource (as published) | Solar |
| Resource category | Solar (normalized for filtering) |
| Proposed online date | 2025-03-01 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Ingham, MI: 11 requests in the MISO queue, 3 active totaling 415 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | METC |
|---|---|
| Cluster | DPP-2019 East (ITC) |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Study Phase: GIA Complete; Post GIA Status: Not Started |
| Queue date | 2019-04-29 |
| Interconnection agreement date | 2022-08-17 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.