MISO request J1355
MISO queue ID J1355
Queue request J1355 was listed in the MISO interconnection queue at the end of 2025 as a 160 MW battery project in Laporte County, IN, according to Berkeley Lab’s queue data file. The filing names Stillwell Subtation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of May 30, 2026.
| Queue ID | J1355 |
|---|---|
| Project name | Not reported |
| Status (as published) | Active |
| Substation | Stillwell Subtation |
| Point of interconnection | Stillwell 138kV Subtation |
| County | Laporte |
| State | IN |
| Voltage | 138 kV |
| Capacity | 160 MW |
| Resource (as published) | Battery |
| Resource category | Battery (normalized for filtering) |
| Proposed online date | 2026-05-30 |
| Source dataset | Berkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025 |
Same substation and county
Laporte, IN: 11 requests in the MISO queue, 7 active totaling 853 MW.
Tracked changes
Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.
Additional filed fields
| Utility | NORTHERN INDIANA PUBLIC SERVICE COMPANY |
|---|---|
| Cluster | DPP-2019 Central |
| Interconnection service | NRIS |
| Project type | Generation |
| Study phase (standardized by Berkeley Lab) | IA Executed |
| Study phase (as the queue printed it) | Study Phase: GIA; Post GIA Status: Not Started |
| Queue date | 2019-04-29 |
Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.
Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.