MISO request J1354

MISO queue ID J1354

Queue request J1354 was listed in the MISO interconnection queue at the end of 2025 as a 146 MW battery project in Decatur County, IN, according to Berkeley Lab’s queue data file. The filing names Decatur County Switching Station as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 15, 2025.

Queue IDJ1354
Project nameNot reported
Status (as published)Active
SubstationDecatur County Switching Station
Point of interconnectionDecatur County 138kV Switching Station
CountyDecatur
StateIN
Voltage138 kV
Capacity146 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2025-10-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Decatur, IN: 11 requests in the MISO queue, 1 active totaling 146 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityHOOSIER ENERGY
ClusterDPP-2019 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2019-04-29
Interconnection agreement date2023-07-19

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.