Substation Scout

Decatur, IN interconnection queue

1 active project totaling 146 MW in the MISO queue, plus 10 with terminal status (shown grayed).

1active projects
146active MW
11total filed
Queue IDProjectkVMWResourceStatus
J1687 Not reported 161 160 Solar Withdrawn
J1717 Not reported 138 150 Solar Withdrawn
J1354 Not reported 138 146 Battery Active
J1715 Not reported 138 145 Solar Withdrawn
J1878 Not reported 138 145 Solar Withdrawn
J1876 Not reported n/r 140 Solar Withdrawn
J804 Not reported 138 119 Solar Withdrawn
J1825 Not reported n/r 100 Solar Withdrawn
J1881 Not reported 161 48 Battery Withdrawn
J1877 Not reported 138 45 Battery Withdrawn
J1879 Not reported 138 43.5 Battery Withdrawn

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.