MISO queue ID J1347

Queue request J1347 was listed in the MISO interconnection queue at the end of 2025 as a 175 MW solar project in Scott County, MS, according to Berkeley Lab’s queue data file. The filing names Pelahatchie - Scott Line Tap as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of June 1, 2023.

Queue IDJ1347
Project nameNot reported
Status (as published)Operational
SubstationPelahatchie - Scott Line Tap
Point of interconnectionPelahatchie - Scott 115 kV Line Tap
CountyScott
StateMS
Voltage115 kV
Capacity175 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2023-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Scott, MS: 4 requests in the MISO queue, 2 active totaling 275 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY MISSISSIPPI
ClusterDPP-2019 South
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: In Service
Queue date2019-04-26
Interconnection agreement date2021-07-13
Operational date2023-06-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first