Scott, MS interconnection queue
2 active projects totaling 275 MW in the MISO queue, plus 2 with terminal status (shown grayed).
2active projects
275active MW
4total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J3680 | Not reported | n/r | 189 | Hybrid | Withdrawn |
| J1347 | Not reported | 115 | 175 | Solar | Operational |
| J4131 | Not reported | 115 | 100 | Battery | Active |
| J3714 | Not reported | 69 | 95 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.