Substation Scout

MISO request J1319

MISO queue ID J1319

Queue request J1319 was listed in the MISO interconnection queue at the end of 2025 as a 117.5 MW wind project in Huron County, MI, according to Berkeley Lab’s queue data file. The filing names Rapson Substation as its point of interconnection. Its status as of December 31, 2025 was “Operational”, with a proposed online date of August 1, 2022.

Queue IDJ1319
Project nameNot reported
Status (as published)Operational
SubstationRapson Substation
Point of interconnectionRapson 120kV Substation
CountyHuron
StateMI
Voltage120 kV
Capacity117.5 MW
Resource (as published)Wind
Resource categoryWind (normalized for filtering)
Proposed online date2022-08-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Rapson Substation substation: 2 requests in the MISO queue, 1 active totaling 117.5 MW.

Queue IDProjectMWResourceStatus
J546Not reported260WindWithdrawn

Huron, MI: 41 requests in the MISO queue, 29 active totaling 4,917.9 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityITC MIDWEST
ClusterDPP-2019 East (ITC)
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: In Service
Queue date2019-04-29
Operational date2022-08-01

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.