MISO request J1308

MISO queue ID J1308

Queue request J1308 was listed in the MISO interconnection queue at the end of 2025 as a 300 MW solar project in Posey County, IN, according to Berkeley Lab’s queue data file. The filing names AB Brown - Gibson Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of April 1, 2024.

Queue IDJ1308
Project nameNot reported
Status (as published)Active
SubstationAB Brown - Gibson Line
Point of interconnectionAB Brown - Gibson 345kV Line
CountyPosey
StateIN
Voltage345 kV
Capacity300 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2024-04-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Posey, IN: 14 requests in the MISO queue, 3 active totaling 750 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilitySouthern Indiana Gas & Electric Company d/b/a Vectren Energy Delivery of Indiana, Inc.
ClusterDPP-2019 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2019-04-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.