Substation Scout

MISO request J1266

MISO queue ID J1266

Queue request J1266 was listed in the MISO interconnection queue at the end of 2025 as a 99 MW solar project in Marion County, IL, according to Berkeley Lab’s queue data file. The filing names Kinmundy - Salem Line as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of July 1, 2025.

Queue IDJ1266
Project nameNot reported
Status (as published)Active
SubstationKinmundy - Salem Line
Point of interconnectionKinmundy - Salem 138kV Line
CountyMarion
StateIL
Voltage138 kV
Capacity99 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2025-07-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Marion, IL: 7 requests in the MISO queue, 4 active totaling 549 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2019 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2019-04-29
Interconnection agreement date2025-11-12

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first