Substation Scout

MISO request J1239

MISO queue ID J1239

Queue request J1239 was listed in the MISO interconnection queue at the end of 2025 as a 100 MW solar project in Ouachita Parish, LA, according to Berkeley Lab’s queue data file. The filing names Rilla Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of October 15, 2024.

Queue IDJ1239
Project nameNot reported
Status (as published)Active
SubstationRilla Substation
Point of interconnectionRilla 115 kV Substation
CountyOuachita Parish
StateLA
Voltage115 kV
Capacity100 MW
Resource (as published)Solar
Resource categorySolar (normalized for filtering)
Proposed online date2024-10-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Ouachita Parish, LA: 16 requests in the MISO queue, 9 active totaling 1,705 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityENTERGY LOUISIANA
ClusterDPP-2019 South
Interconnection serviceERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Construction
Study phase (as the queue printed it)Study Phase: GIA Complete; Post GIA Status: Under Construction
Queue date2019-04-29
Interconnection agreement date2021-11-29

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first