Queue request J1229 was listed in the MISO interconnection queue at the end of 2025 as a 50 MW battery project in Muscatine County, IA, according to Berkeley Lab’s queue data file. The filing names Sub 92 Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 30, 2026.

Queue IDJ1229
Project nameNot reported
Status (as published)Active
SubstationSub 92 Substation
Point of interconnectionSub 92 345 kV Substation
CountyMuscatine
StateIA
Voltage345 kV
Capacity50 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2026-06-30
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Muscatine, IA: 7 requests in the MISO queue, 6 active totaling 585.4 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityMIDAMERICAN ENERGY COMPANY
ClusterDPP-2019 West
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA In Process; Post GIA Status: Not Started
Queue date2019-04-29
Interconnection agreement date2023-01-26

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first