Substation Scout

MISO request J1200

MISO queue ID J1200

Queue request J1200 was listed in the MISO interconnection queue at the end of 2025 as a 24.2 MW hybrid project in Putnam County, IL, according to Berkeley Lab’s queue data file. The filing names Putnam Substation as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of June 1, 2024.

Queue IDJ1200
Project nameNot reported
Status (as published)Active
SubstationPutnam Substation
Point of interconnectionPutnam 138kV Substation
CountyPutnam
StateIL
Voltage138 kV
Capacity24.2 MW
Resource (as published)Solar+Battery
Resource categoryHybrid (normalized for filtering)
Proposed online date2024-06-01
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Putnam, IL: 9 requests in the MISO queue, 6 active totaling 647.1 MW.

Tracked changes

Not tracked. MISO rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityAMEREN ILLINOIS
ClusterDPP-2019 Central
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)Study Phase: GIA; Post GIA Status: Not Started
Queue date2019-04-25
Interconnection agreement date2022-08-22
Components (hybrid)Solar 24.2 MW + Battery

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.