Putnam, IL interconnection queue
6 active projects totaling 647.1 MW in the MISO queue, plus 3 with terminal status (shown grayed).
6active projects
647.1active MW
9total filed
| Queue ID | Project | kV | MW | Resource | Status |
|---|---|---|---|---|---|
| J2554 | Not reported | n/r | 220 | Solar | Active |
| J2311 | Not reported | n/r | 145 | Wind | Active |
| G914 | Not reported | 138 | 137 | Wind | Withdrawn |
| J2551 | Not reported | n/r | 110 | Battery | Active |
| J3351 | Not reported | n/r | 100 | Battery | Withdrawn |
| J3899 | Not reported | n/r | 100 | Solar | Active |
| J2312 | Not reported | n/r | 47.9 | Wind | Active |
| J1200 | Not reported | 138 | 24.2 | Hybrid | Active |
| J3560 | Not reported | 138 | 20 | Solar | Withdrawn |
A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with MISO before relying on these figures.